Ground Settlement of High-Permeability Sand Layer Induced by Shield Tunneling: A Case Study under the Guidance of DBN
Table 3
Engineering control standards.
| Monitoring project | Control value (mm) | Cumulative warning value | Yellow | Orange | Red |
| Ground settlement | -30 mm | -21 mm | -25.5 mm | -30 mm | (Bulge) | +10 mm | +7 mm | +8.5 mm | +10 mm | Segment uplifting | +20 mm | +10 mm | +15 mm | +20 mm |
|
|