Numerical Simulation of Soil Displacement and Settlement in Deep Foundation Pit Excavations Near Water

Table 1

Sequence of construction for the Yellow River Tunnel.

Construction procedureConstruction contentJob content

1First-order precipitationWater level dropped to 88.0 m
2First-stage excavationEarthwork was excavated to 89.5 m
3First horizontal bracePerform the first bar at 90.9 m
4SecondWater level dropped to 83.0 m
5SecondEarthwork was excavated to 84.6 m
6Second horizontal braceMake the first bar at 85.4
7Third-order precipitationWater level dropped to 77.2 m
8Third-stage excavationEarthwork was excavated to 78.7 m
9Third horizontal braceMake the first bar at 80.7 m
10Fourth-stage precipitationWater level dropped to 72.6 m
11Fourth orderEarthwork was excavated to 73.4 m
12Fourth horizontal braceMake the first bar at 75.6 m
13Fifth-level precipitationWater level dropped to 70.0 m
14Fifth-stage excavationEarthwork was excavated to 71.0 m