Study on the Factors Affecting the Quality of Trench Cutting Remixing Deep Wall in Qingdao Area

Figure 3

Schematic diagram showing the steps of the TRD method. (a) Insert the saw chain cutters. (b) Cut and mix the soil mass and inject bentonite slurry. (c) Inject cement slurry and mix. (d) Go to the next section. (e) Pull out the cutters after having completed.
(a)
(b)
(c)
(d)
(e)