Investigation on Dewatering of a Deep Shaft in Strong Permeable Sandy Pebble Strata on the Bank of the Yellow River

Table 7

Operation scheme of pumping wells.

StageNumber of pumping wellsWater table (m)Excavation depth (m)Description
Area IArea IIArea IIIArea IArea II

1-10.0-10.00.00~10.00Excavation of F1
22-18.4-10.010.00~17.68
34-25.6-10.017.68~24.08Excavation of F2
46-32.5-10.024.08~30.48Excavation of F3
Grouting the base during the excavation of F3 with the target permeability coefficient of
5164-54.2-17.430.48~35.50Excavation of F4
61612-54.2-20.135.50~36.78
71624-54.4-24.136.78~39.00Excavation of F5
81640-54.8-28.839.00~42.00
91652-54.8-34.242.00~45.10