Risk Assessment Study on Mechanical Connecting Aisle Construction in the Bohai Mudstone Stratum with High Water Pressure

Table 11

Risk correction matrix.

RBSWBS
Cumulative value of riskSort

0.4320.36000000.36000.6120.4320.360000.4322.9886
0.3770.3480.3480.3480.3480.3480.46400.5510.4060.2900.4060.3770.3774.9883
0.4320.6840.6840.6840.6840.6840.68400.6840000.6840.4326.3361
000000000.9100.91000001.8208
00000000.4900.4200.49000.350001.7509
00000.33600.24000.384000000.96014
000000000.162000.210000.37220
000000000.384000.3360.26400.98413
00000.16000.1760.1920.208000000.73616
0000000.2600.2800.260000000.80015
0.180000.1440.1440.1200.2040.1200.15600.18000.1440.1801.57210
0000000.13000.1820.15600.182000.65018
0000000.18000.1980.21600000.59419
000000.1210.1100.1320.1430.16500000.67117
00.2160.2160.216000.3240.2340.270000001.47611
0.1950000.1560000.1560.1300.1560.1950.1690.1951.35212
000000000.208000000.20821
0.704000000.6080.6400.51200.320000.7683.5525
0.6600000.66000.79200.79200.6160.6160.4840.6605.2802
00000.4590000.5400.59400.702002.2957
0.720000000.52000.4800.4400.20000.6400.7203.7204
Cumulative value of risk3.7001.6081.2481.3922.9471.2735.0522.0888.2123.9392.1222.9972.7623.764
Sort5111412713210139684