Research Article
Risk Assessment Study on Mechanical Connecting Aisle Construction in the Bohai Mudstone Stratum with High Water Pressure
Table 4
Risk probability and consequence level criteria.
| Grade | Probability of occurrence | The probability value interval | The consequences are severe heaviness | Casualties
| Engineering quality
| Economic loss
| Environmental impact
| Delays in construction
|
| 5 | Frequent | | Serious | Causes a small amount death of persons | Impact on maximum quality | The losses are enormous | Maximum | Delays of more than 90 days | 4 | Accidental | | Dangerous | Lead to individual death of persons | Important impact on quality | Important | Important | Delay 60-90 days | 3 | Infrequent | | Momentous | Causes a small amount injuries were made | Larger impact on quality | Larger | Larger | Delay 30-60 days | 2 | Not very frequent Cumbersome | | Not dangerous | Lead to individual injuries | Smaller impact on quality | Smaller | Smaller | Delay 10-30 days | 1 | Rare | | Negligible | It will not cause casualties | Does not influence quality | Small | Small | Delays of less than 10 days |
|
|