Risk probability and consequence level criteria.

GradeProbability of occurrenceThe probability value intervalThe consequences are severe heavinessCasualties
Engineering quality
Economic loss
Environmental impact
Delays in construction

5FrequentSeriousCauses a small amount death of personsImpact on maximum qualityThe losses are enormousMaximumDelays of more than 90 days
4AccidentalDangerousLead to individual death of personsImportant impact on qualityImportantImportantDelay 60-90 days
3InfrequentMomentousCauses a small amount injuries were madeLarger impact on qualityLargerLargerDelay 30-60 days
2Not very frequent
Cumbersome
Not dangerousLead to individual injuriesSmaller impact on qualitySmallerSmallerDelay 10-30 days
1RareNegligibleIt will not cause casualtiesDoes not influence qualitySmallSmallDelays of less than 10 days