Identification and Treatment of Collapse and Mud Inrush Caused by Deep Karst Trough in Tunnels

Table 2

Revealed karst caves before mud inrush and collapse.

Serial no.ChainageLocationSize of the karst cavesFilling status

1GK0+398Left side of tunnel faceThe karst fissure developed along the longitudinal direction of the tunnel at 15°, with a width of about 2 m, a height of 17 m, and a length of 16 m.Wet inside the cavity, without fissure water, filled with mud
2GK0+400Right side of tunnel faceThe karst cave is 3.6 m long and 4 m wide upward along the tunnel, and the vertical height above the vault is 7.5 m.Wet inside the cavity, without fissure water, filled with mud
3GK0+405The right sidewallThe karst cave extends downward, with a diameter of 3.5 m and a visible depth of about 6.5 m.No filling