Supporting Mechanism of Pile-Anchor Systems for Deep Foundation Pits in Alpine Regions during the Spring Thaw

Table 1

Design parameters of the prestressed anchor cables.

Anchor cableLength of anchor cable (m)Steel strandDiameter of anchoring body (mm)Horizontal inclination (°)Axial force standard value (kN)Preaxial force (kN)
Overall lengthLength of anchorage sectionLength of free section

First21.013.08.025015/1377.860
Second23.016.07.025015/13169.8122
Third27.020.07.025015/13329.1244
Fourth24.017.07.025015/13453.1325
Fifth15.010.05.025015/13312.0256