A Data-Driven Artificial Neural Network Approach to Software Project Risk Assessment
Table 3
The splitting of data for the training of ANN was taken an 80–20 distribution.
| Project no. | Complexity | Financial | Performance | Schedule | User | Total PR |
| 1 | 0 | 0.01 | 0.08 | 0.04 | 0.04 | 0.034 | 2 | 0.01 | 0.01 | 0.01 | 0.02 | 0.08 | 0.01 | 3 | 0.08 | 0.02 | 0.01 | 0.04 | 0.01 | 0.032 | 4 | 0.06 | 0.01 | 0.01 | 0.02 | 0.02 | 0.024 | 5 | 0.42 | 0.15 | 0.04 | 0.07 | 0.21 | 0.164 | 6 | 0.04 | 0.05 | 0.2 | 0.03 | 0.04 | 0.066 | 7 | 0.02 | 0.04 | 0.3 | 0.12 | 0.1 | 0.116 | 8 | 0.02 | 0.13 | 0.2 | 0.18 | 0.01 | 0.08 | 9 | 0.24 | 0.10 | 0.16 | 0.2 | 0.05 | 0.09 | 10 | 0.03 | 0.28 | 0.12 | 0.4 | 0.25 | 0.216 | 11 | 0.12 | 0.08 | 0.03 | 0.01 | 0.04 | 0.056 | 12 | 0.03 | 0.06 | 0.09 | 0.04 | 0.06 | 0.056 | 13 | 0.12 | 0.08 | 0.03 | 0.01 | 0.04 | 0.056 |
|
|