Research Article
Environmental Life-Cycle Analysis of Hybrid Solar Photovoltaic/Thermal Systems for Use in Hong Kong
Table 6
Evaluation of cost payback time.
| | Investment: HK$ | Free-stand PV/T [6] | BiPV/T [7] |
| | Water storage tank | 400 | 750 | | Collector frame and support | 400 | 1800 | | Modular thermal absorber | 600 | 2700 | | Solar cells and encapsulation | 4000 | 17500 | | Inverter | 700 | 1000 | | Piping, wiring and accessories | 300 | 900 | | Installation costs | 1500 | 3000 |
| | Total system costs (HK$) | 7900 | 27650 |
| | Useful energy savings | MJ (kWh) | MJ (kWh) |
| | Thermal energy | 2650.4 (736.2) | 8127.5 (2257.6) | | Electrical energy | 473.2 (131.4) | 1162.4 (322.9) | | Space cooling load | — | 742.6 (206.3) |
| | Cost savings: HK$ | | |
| | Gaseous fuel at HK$0.2/MJ | 530.1 | 1625.5 | | Electricity at HK$0.95/kWh | 124.9 | 372.0 | | Annual saving | 655.0 | 1997.5 |
| | Cost payback time (CPBT) | 12.1 years | 13.8 years |
|
|
Note: USD1 is equivalent to HK$7.8.
|