Research Article

Optimal Recloser Placement in Distribution System Considering Maneuver Points, Practical Limitations, and Recloser Malfunction

Table 3

Reliability indices and optimal solutions of three scenarios for different number of reclosers in RBTS-Bus2.

ScenarioSAIFI (Int/cr)SAIDI (hr/cr)CAIDI (hr/crI)ENS (kWh)OFORPOMPPONP

One REC
10.249213.565214.30637.3573.67522PredeterminedUnlimited
20.249213.565214.30637.3573.675224,6,10,14Unlimited
30.249213.566214.31037.7113.684423,5,10,14(F1-F2), (F3-F4)

Two RECs
10.249213.536214.19036.9363.65062, 9PredeterminedUnlimited
20.249213.508314.07737.1893.64002, 94,6,9,13Unlimited
30.249213.536314.19037.1313.65542, 94,6,10,14(F1-F2), (F3-F4)

Three RECs
10.249213.507314.07436.6523.62942, 9, 10PredeterminedUnlimited
20.249213.478913.95936.9963.62372, 3, 103, 6, 9, 13Unlimited
30.249213.507414.07436.8743.63422, 9, 104, 6, 10, 14(F1-F2), (F3-F4)