Providing a New Multiobjective Two-Layer Approach for Developing Service Restoration of a Smart Distribution System by Islanding of Faulty Area

Table 4

Second layer results from fault between buses 4 and 5.

TimeOptimal load planningNondispatchable resources planning
SOCPower (kW)BusNetwork sections
Load sheddingLoad outage
Power (kW)Power (kW)

19:00913.513434.112ExchangeSection connected to the upstream
91.45261.693ES20
30−15.789ES5MG 1
650MT29
106.66739ES14MG 2
511.743MT15
349.3MT18MG 4

20:001012.724515.188ExchangeSection connected to the upstream
4046.307ES20
650MT29MG 1
554.394MT15MG 2
3069ES14
338.7MT18MG 4
4054ES33