A Cost and Passenger Responsible Optimization Method for the Operation Plan of Additional High-Speed Trains in a Peak Period

Table 5

Loading capacities, passenger demand, and supply capacity (unit: person).

StationLoading capacity of each trainPassenger demand in peak periodSupply capacity of existing trainsSupply capacity of the new operation plan

Wuhan205450036004500
Xianning North50175100150
Chibi North4016040160
Yueyang East187150012001440
Miluo East100225150200
Changsha South293650052006500
Zhuzhou West12510006001000
Hengshan West100400400400
Hengyang East150125010001250
Leiyang West170375280350
Chenzhou West1601000640896
Shaoguan200150011201440
Qingyuan100200135180
Guangzhou North70280210280
Total—190651467518746