Research Article
Payment Scheduling Problem with Multiple Modes for Activities to Maximize the Net Present Value of a Project
Table 2
Operators, parameters, and their levels (GA).
| Factor | Symbol | Level | Type |
| Temp | | Small problems | B(1) = 10, B(2) = 20, B(3) = 30 | Medium problems | B(1) = 40, B(2) = 50, B(3) = 60 | Large problems | B(1) = 80, B(2) = 100, B(3) = 120 |
| Repeat | | Small problems | C(1) = 0.6, C(2) = 0.7, C(3) = 0.8 | Medium problems | C(1) = 0.7, C(2) = 0.8, C(3) = 0.9 | Large problems | C(1) = 0.7, C(2) = 0.8, C(3) = 0.9 |
| | | Small problems | C(1) = 0.05, C(2) = 0.07, C(3) = 0.09 | Medium problems | B(1) = 0.05, B(2) = 0.07, B(3) = 0.09 | Large problems | B(1) = 0.05, B(2) = 0.07, B(3) = 0.09 |
|
|