Payment Scheduling Problem with Multiple Modes for Activities to Maximize the Net Present Value of a Project

Table 2

Operators, parameters, and their levels (GA).

FactorSymbolLevelType

TempSmall problemsB(1) = 10, B(2) = 20, B(3) = 30
Medium problemsB(1) = 40, B(2) = 50, B(3) = 60
Large problemsB(1) = 80, B(2) = 100, B(3) = 120

RepeatSmall problemsC(1) = 0.6, C(2) = 0.7, C(3) = 0.8
Medium problemsC(1) = 0.7, C(2) = 0.8, C(3) = 0.9
Large problemsC(1) = 0.7, C(2) = 0.8, C(3) = 0.9

Small problemsC(1) = 0.05, C(2) = 0.07, C(3) = 0.09
Medium problemsB(1) = 0.05, B(2) = 0.07, B(3) = 0.09
Large problemsB(1) = 0.05, B(2) = 0.07, B(3) = 0.09