Different indicators of IEEE 1366-2012 and DL/T 836-2016.

Indicator typeIndicator nameSource of indicator

Short-term outage indicatorsAverage frequency of short-term outage events (MAIFIE)IEEE1366-2012
Index of power outage usersAverage number of customers with outages (MIC)DL/T836-2016
Average number of prescheduled outages
Average number of customers with fault outages
Power shortage indexAverage outage shortage of electricity to customers (AENS)
Average outage shortage of power for prescheduled outages
Average outage shortage of power
Average duration of power failurePrescheduled outage mean duration
Mean duration of fault outages
Indicators considering external impactExternal impact outage rate (IRE)
Facility-based indicatorsFacility outage rate (FEOI)
Mean duration of facility outages (MDEOI)
 Line fault outage rate (FLFI) 
Fault outage rate on overhead lines (FOLFI)
Cable line fault outage rate (FCFI)
Distribution transformer fault outage rate (FTFI)
Outgoing circuit breaker fault outage rate (FCBFI)