Research Article

Application of Digital Twins to Flexible Production Management: Taking a Shandong Factory as an Example

Table 1

Show the issues that arose throughout the debugging process.

Serial numberProblems in case debugging

1The program is not working.
2The software system’s assignment is erroneous, resulting in a disordered program
3The platform equipment’s height is improper, and the stacker cannot take up the products.
4The motor’s rotational direction is incorrect and cannot transport the material.
5The material could not be transported from station A to station B because the signal transmission between the two stations failed.
6Poor power contact of a motor causes the conveyor to be unstable.
7The frequency of wireless transmission is wrong, and the signal transmission fails.
8A disturbed scheduler leads to inefficient equipment.