A Novel Assembly Line Balancing Method Based on PSO Algorithm

Table 4

The job element of antenna assembly.

Operation sequenceNumber job elementStandard work time (s)

1Put the chassis on the assembly line and clean3.4
2Install the high frequency oscillator6.96
3Install the wall components5.29
4Install the input cable components2.58
5Install the high frequency isolation12.13
6Install the low frequency isolation3.9
7Install high frequency isolation block4.2
8Install low frequency oscillator10.46
9Low frequency cable wiring6.12
10High frequency cable wiring10
11Install low frequency ground plate12.59
12The high frequency oscillator cable welding to the oscillator21.8
13Install high frequency ground plate12.98
14Install the low frequency oscillator cable in place9.29
15Install low frequency switching4.38
16Low frequency cable welding and cleaning28.29
17Install the high frequency oscillator cable in place8.43
18The high frequency cable welding and cleaning22.66
19Place the low frequency phase shifter components1.76
20Place the high frequency phase shifter components1.63
21Install low frequency flat6.14
22Install high frequency flat4.97
23Low frequency plate welding26.9
24High frequency plate welding33.43
25Install phase shift11.63
26Fixed the guide box and the front panel5.23
27The support installation3.07
28Install support7.37