Efficient Heuristic Algorithm for Scheduling Two-Stage Hybrid Flowshop with Sequence-Dependent Setup Times

Table 12


For For
#Candidate solutionsMakespan#Candidate solutionsMakespan

12-1-6-4-3-557116-4-3-2-1-5571
22-1-6-4-5-357126-4-3-2-5-1607
32-1-6-5-4-367736-4-3-5-2-1647
42-1-5-6-4-365846-4-5-3-2-1610
52-5-1-6-4-362656-5-4-3-2-1612
65-2-1-6-4-367265-6-4-3-2-1633

Best solution among all candidate solutions in this step.
Three different solutions have the same minimum makespan.