Comparing the objectives in Phase 2 between the initial feasible, the optimal, and the reference solutions.

 ATCo work and rest periods and positionsControl center changesATCo workloads
Subobject. 1Subobject. 2Subobject. 3Number of rest periodsMinMax

Initial sol.1.5, 1.5, 20.7%3.6, 21.8, 21.8%7, 9, 105687.38120390
Optimal sol.34.7, 34.7, 68.4%8.3, 41.6, 41.6%13, 13, 133530.91210315
Reference sol.20, 20, 100%0, 27.2, 27.2%10, 11, 133458.42180345