A Novel Incipient Evaluation Method for Postconstruction Settlement by Using a Statistic Approach with Time-Extended Loading Test
Table 8
Construction parameters for selected subgrade sections.
No.
Pile type
Pile
diameter
Pile
length
spacing
Bearing Capacity Design
Characteristics
1
Cement mixing pile
0.5
13
1.2
240
2
CFG pile
0.4
12
2.0
280
3
Tube pile
0.3
22
2.6
310