Primary index | Secondary index | Risk weight | Risk accident rate | Risk control cost (10,000 yuan) | Loss from risk (10,000 yuan) |
|
Personnel risk factor | Man-machine mixed operation | 0.016 | 0.53 | 0.95 | 24.25 |
High-altitude operation | 0.035 | 0.69 | 3.12 | 25.60 |
Fatigue construction caused by high-intensity operation | 0.019 | 0.55 | 2.22 | 7.65 |
Illegal operation by builders | 0.053 | 0.61 | 1.90 | 12.30 |
Lack of professional technicians | 0.033 | 0.54 | 0.92 | 17.95 |
Poor quality and weak safety awareness of personnel | 0.011 | 0.43 | 1.35 | 25.80 |
|
Mechanical risk factor | Improper operation, maintenance, and safety inspection of equipment | 0.056 | 0.48 | 1.15 | 34.45 |
Unreasonable selection and layout of transporting, hoisting, and grouting equipment | 0.037 | 0.33 | 2.87 | 6.25 |
Equipment failure, aging | 0.074 | 0.63 | 2.82 | 12.70 |
|
Material risk factor | Unqualified safety protection items related to construction | 0.078 | 0.59 | 4.62 | 28.70 |
Nonstandard building materials used in the construction | 0.050 | 0.46 | 4.22 | 21.80 |
Arbitrary stacking of construction materials | 0.039 | 0.32 | 2.12 | 9.30 |
|
Environmental risk factor | Narrow working surface, insufficient lighting | 0.071 | 0.36 | 1.97 | 12.80 |
Improper protection measures for borders and openings | 0.066 | 0.45 | 1.30 | 16.80 |
Presence of hazardous sources like charged high-voltage wires and underground gas pipelines around the construction site | 0.016 | 0.29 | 2.45 | 34.90 |
Awful weather | 0.014 | 0.31 | 1.80 | 18.25 |
|
Technological risk factor | Defects in safety protection and management technologies such as temporary support system | 0.066 | 0.58 | 2.62 | 11.30 |
Defects in construction technologies such as hoisting equipment attachment measures | 0.056 | 0.39 | 1.47 | 6.75 |
Defects in construction techniques such as prefabricated component assembly and key part processing | 0.045 | 0.64 | 0.82 | 22.95 |
|
Management risk factor | Lack of relevant safety education or training | 0.066 | 0.54 | 1.87 | 29.80 |
Mismatch between the safety management system and actual construction conditions | 0.026 | 0.49 | 1.60 | 14.45 |
Lack of unified, effective management standards or supervision mechanism | 0.032 | 0.58 | 3.55 | 49.35 |
Improper multiparty coordination management during construction | 0.043 | 0.61 | 2.80 | 32.65 |
|