Research Article
Multiobjective Optimization of Safety Risk of Prefabricated Building Construction considering Risk Correlation
Table 2
Risk pairs with risk correlations.
| No. | Correlated risk pair | Loss from a single risk (10,000 yuan) | Loss from concurrent risks (10,000 yuan) |
| 1 | Lack of professional technicians | 17.95 | 29.40 | Defects in construction techniques such as prefabricated component assembly and key part processing | 22.95 |
| 2 | Illegal operation by builders | 12.30 | 72.22 | Improper operation, maintenance, and safety inspection of equipment | 34.45 |
| 3 | Poor quality and weak safety awareness of personnel | 25.80 | 37.20 | Lack of relevant safety education or training | 29.80 |
| 4 | Nonstandard building materials used in the construction | 21.80 | 55.31 | Lack of unified, effective management standards or supervision mechanism | 49.35 |
| 5 | Arbitrary stacking of construction materials | 9.30 | 20.79 | Mismatch between safety management system and actual construction conditions | 14.45 |
| 6 | High-altitude operation | 25.60 | 62.64 | Improper protection measures for borders and openings | 16.80 |
| 7 | Narrow working surface, insufficient lighting | 12.80 | 43.59 | Awful weather | 18.25 | ā |
|
|