Research Article

Safety Assessment in Road Construction Work System Based on Group AHP-PCA

Table 8

Road construction safety assessment indicators’ final weights and ranking based on group AHP-PCA and traditional GAHP.

CriteriaWeightsSubcriteriaLocal weightsGlobal weightsRanking
GAHP-PCAGAHPGAHP-PCAGAHPGAHP-PCAGAHPGAHP-PCAGAHP

Human factors (A)0.29350.3330Work attitude (A1)0.22350.23410.06560.078032
Body condition (A2)0.11640.13620.03420.04541310
Professional skill (A3)0.35970.26480.10560.088211
Safety consciousness (A4)0.15790.18740.04630.062473
Psychological quality (A5)0.14250.17750.04180.059194

Material factors (B)0.11910.1272Material quality (B1)0.36210.34620.04310.0440811
Storage condition (B2)0.15130.17520.01800.02232221
Sorting status (B3)0.07020.12030.00840.01532723
Applicability feasibility (B4)0.21870.16470.02600.02091922
Effectiveness (B5)0.19770.19360.02350.02462117

Equipment factors (C)0.17140.1927Equipment selection (C1)0.15870.14620.02720.02821816
Running state (C2)0.23640.25620.04050.0494108
Maintenance condition (C3)0.31250.29510.05360.056956
Protective measures (C4)0.29240.30660.05010.059165

Management factors (D)0.26630.2041Previous preparation (D1)0.24350.26210.06480.053547
Safety facilities (D2)0.11780.11240.03140.02291620
Safety education (D3)0.24870.23510.06620.048029
Safety check (D4)0.13210.15310.03520.03121213
Technical clarification (D5)0.10980.05430.02920.01111725
Emergency measures (D6)0.14810.18300.03940.03741112

Environmental factors (E)0.14970.1429Geographical environment (E1)0.09120.08120.01370.01162424
Underground pipeline (E2)0.04210.06410.00630.00922826
Surrounding buildings (E3)0.08740.05210.01310.00742528
Weather effect (E4)0.06210.05320.00930.00762627
Working environment (E5)0.11450.21400.01710.03062314
Traffic condition (E6)0.16820.16320.02520.02332019
Construction condition (E7)0.21490.16740.03220.02391518
Site safety facilities (E8)0.21960.20480.03290.02931415