A Solution Approach to the Daily Dockworker Planning Problem at a Port Container Terminal

Table 1

The results obtained by both approaches.

Problem size (the number of ships)InstanceIntegrated approachSequential approachDifference in total costs (%)
GZ [€] (1)GZ [€] (2)

1012521938.43430470.428.00
22218457.83026653.830.75
32420989.23430469.231.11
42219085.43027958.231.74
52017192.43026116.234.17
1162218137.42927160.233.22
72723799.63632348.426.43
82521904.83430453.628.07
92521902.43429863.226.66
102420963.43733305.437.06
12112723850.03430486.021.77
122723807.43329534.419.39
132723823.04137113.035.81
142723815.23834243.230.45
152320051.43329411.431.82
13162925729.24036157.228.84
172824791.43733323.425.60
182723842.23531450.224.19
192320023.23632371.238.15
202521929.43228883.424.08
14212824764.43935192.429.63
223228572.04137104.022.99
233228568.43632384.411.78
243329511.04439939.026.11
253329539.24540915.227.80
15263430459.04138991.021.88
272824781.23632365.223.43
282824780.03632364.023.43
293228574.44439950.428.48
303127617.44137097.425.55
16313430461.44137097.417.89
322925721.43631645.218.72
333127599.44036131.423.61
343430451.24137087.217.89
352925730.43531598.418.57