Evaluation of the Adaptability of an EPB TBM to Tunnelling through Highly Variable Composite Strata
Table 8
Primary evaluation indexes for the adaptability of an EPB TBM during tunnelling.
| Target layer | Adaptability degree of EPB TBM under mixed ground conditions D |
| Criteria layer | EPB TBM design U1 | Tunnelling method U2 | Geological conditions U3 | Environment conditions U4 | Index layer | Total thrust W1 Cutterhead structure W2 Cutterhead torque W3 Cutterhead opening ratio W4 Muck improvement technique W5 Selection and layout of cutters W6 Cutter spacing W7 Muck amount of screw conveyor W8 | Advancing speed W9 Rotating speed of cutterhead W10 Earth pressure in cutterhead chamber W11 Shield tail void W12 Wall-back grouting pressure W13 | Artificial fill W14 Soft soil stratum W15 Liquefied sand layer W16 Residual soil layer W17 Composite strata W18 Microweathered granite protrusions W19 Hard-rock layer W20 Fault crushed zone W21 Spherical weathered boulders W22 | Underground structures W23 Ground buildings W24 Structure of existing tunnel lines W25 |
|
|