Engineering | Risk event | Risk source |
|
A1: pile foundation construction | B1: equipment transportation and installation | C1: drill rack installation tilt |
C2: falling to the ground during equipment transportation |
C3: incorrect installation of drill frame |
C4: unstable construction platform |
B2: burying of protective cylinders | C5: the height of the protective tube is not enough |
C6: the seam of the protective tube is not dense |
C7: insufficient insertion depth of the protective tube |
C8: the protective tube is inclined and leaking |
C9: unstable water head in the protection tube |
B3: drilling holes | C10: unqualified wall protection mud quality |
C11: bore hole tilt |
C12: borehole collapse |
C13: plum blossom holes |
C14: drilling rig shift |
C15: reaming or shrinking |
C16: hole leakage |
C17: the rig is malfunctioning |
C18: paste drill, buried drill |
B4: cleaning hole | C19: collapse when clearing the hole |
C20: incomplete clearance |
C21: the thickness of the sediment does not meet requirements |
C22: the mud thickness does not meet the requirements |
B5: lifting of steel cages | C23: skeleton deformation |
C24: the skeleton collides with the hole wall when lifting |
C25: unqualified welding quality |
C26: the skeleton elevation does not meet the requirements |
B6: pouring underwater concrete | C27: catheter inlet |
C28: collapse during pouring |
C29: pipe stuck |
C30: buried pipe |
C31: broken piles |
C32: pile body concrete enters mud |
C33: leakage and deviation of reinforcement skeleton |
|