Analysis of Diaphragm Wall Deflection Induced by Excavation Based on Machine Learning

Table 4

Construction procedures in Area I.

StageConstruction details
Area IArea II

1Excavate to −0.1 mExcavate to −0.1 m
Install concrete struts (800 × 1000) at −0.5 mInstall concrete struts (800 × 1000) at −0.5 m

2Excavate to −4.9 mExcavate to −6.35 m
Install steel struts (Φ609/t = 16) at −4.4 mInstall steel struts (Φ609/t = 16) at −5.85 m

3Excavate to −8.4 mExcavate to −9.95 m
Install concrete struts (1000 × 1000) at −7.9 mInstall concrete struts (1000 × 1000) at −9.45 m

4Excavate to −13.76 mExcavate to −13.75 m
Install concrete struts (1200 × 1000) at −13.26 mInstall steel struts (Φ609/t = 16 mm) at −13.25 m

5Excavate to −17.76 mExcavate to −16.54 m
Install double steel struts (Φ609/t = 16) at −17.26 mInstall concrete struts (1200 × 1000) at −16.04 m

6Excavate to −21.26 mExcavate to −21.26 m
Install steel struts (Φ609/t = 16) at −20.76 mInstall steel struts (Φ609/t = 16 mm) at −20.76 m

7Excavate to −25.70 mExcavate to −25.60 m
Pour bottom slabPour bottom slab