Construction procedures in Area I.
| Stage | Construction details | Area I | Area II |
| 1 | Excavate to −0.1 m | Excavate to −0.1 m | Install concrete struts (800 × 1000) at −0.5 m | Install concrete struts (800 × 1000) at −0.5 m |
| 2 | Excavate to −4.9 m | Excavate to −6.35 m | Install steel struts (Φ609/t = 16) at −4.4 m | Install steel struts (Φ609/t = 16) at −5.85 m |
| 3 | Excavate to −8.4 m | Excavate to −9.95 m | Install concrete struts (1000 × 1000) at −7.9 m | Install concrete struts (1000 × 1000) at −9.45 m |
| 4 | Excavate to −13.76 m | Excavate to −13.75 m | Install concrete struts (1200 × 1000) at −13.26 m | Install steel struts (Φ609/t = 16 mm) at −13.25 m |
| 5 | Excavate to −17.76 m | Excavate to −16.54 m | Install double steel struts (Φ609/t = 16) at −17.26 m | Install concrete struts (1200 × 1000) at −16.04 m |
| 6 | Excavate to −21.26 m | Excavate to −21.26 m | Install steel struts (Φ609/t = 16) at −20.76 m | Install steel struts (Φ609/t = 16 mm) at −20.76 m |
| 7 | Excavate to −25.70 m | Excavate to −25.60 m | Pour bottom slab | Pour bottom slab |
|
|