The operation time of different processes of processing each component of each work team.

ComponentProcessOptional task forceProcessing time/h

Columnk1A1, A2, A3, A4, A50.6, 0.8, 0.9, 1, 0.7
k2A1, A2, A3, A4, A53.3, 2.7, 3.5, 4.5, 3.3
k3A1, A2, A3, A4, A51.8, 1.8, 1.6, 2.3, 1.8
k4A1, A2, A3, A4, A55.5, 5.5, 5.5, 5.5, 5.5
k5A1, A2, A3, A4, A50.5, 0.6, 0.6, 0.7, 0.3

Beamk1A1, A2, A3, A4, A50.5, 0.6, 0.8, 0.9, 0.6
k2A1, A2, A3, A4, A53.6, 3, 3.7, 4.8, 3.7
k3A1, A2, A3, A4, A51.6, 1.6, 1.4, 2.1, 1.6
k4A1, A2, A3, A4, A55.5, 5.5, 5.5, 5.5, 5.5
k5A1, A2, A3, A4, A50.4, 0.5, 0.5, 0.6, 0.3

Boardk1A1, A2, A3, A4, A50.3, 0.5, 0.6, 0.6, 0.4
k2A1, A2, A3, A4, A53.3, 2.8, 3.6, 4.7, 3.5
k3A1, A2, A3, A4, A52.5, 2.5, 2, 3, 2.6
k4A1, A2, A3, A4, A55.5, 5.5, 5.5, 5.5, 5.5
k5A1, A2, A3, A4, A50.3, 0.4, 0.4, 0.6, 0.2

Stairsk1A1, A2, A3, A4, A50.9, 1.1, 1.2, 1.4, 1
k2A1, A2, A3, A4, A54, 3.5, 4.2, 6, 4.2
k3A1, A2, A3, A4, A51.4, 1.4, 1.3, 1.7, 1.5
k4A1, A2, A3, A4, A55.5, 5.5, 5.5, 5.5, 5.5
k5A1, A2, A3, A4, A50.7, 0.9, 0.9, 1, 0.5

Shear wallk1A1, A2, A3, A4, A50.3, 0.5, 0.6, 0.6, 0.4
k2A1, A2, A3, A4, A53.6, 3, 3.7, 4.8, 3.7
k3A1, A2, A3, A4, A52.5, 2.5, 2, 3, 2.6
k4A1, A2, A3, A4, A55.5, 5.5, 5.5, 5.5, 5.5
k5A1, A2, A3, A4, A50.3, 0.4, 0.4, 0.6, 0.2