Investment Risk Assessment of EPC Power Transmission and Transformation Projects under New Energy Grid Connection Based on the Owner’s Perspective

Table 1

Differences between traditional project contracting mode and EPC mode in PTTPs.

ComparisonsTraditional project contracting modeEPC mode

Main mode differencesThe tasks of design, procurement, and construction are undertaken by different contractors in chronological orderEPC general contractor undertakes the tasks of design, procurement, and construction, and all tasks can be coordinated in time dimension
CoordinationOwner’s external coordination with low efficiencyInternal coordination of the general contractor with high efficiency
Application scopeSmall or medium-sized projectsLarge-scale projects
Construction progress controlMore difficult in coordination and controlLess difficult in coordination and control
Owner’s participationDeeper participationShallow participation
Total project costsHigher costsLower costs
Owner’s management costsHigher costsLower costs