Research Article

Multiobjective Project Scheduling with Multiple Compression Capabilities of the Multistate Activities with Project Reliability Approach using the Metaheuristic Algorithm

Table 1

Time and description of the activity of the central operation facilities project.

Activity nameActivity descriptionPrerequisite for activityActivity timeTimeFloating time
ESEFLSLF

AEngineering04040
BProcurement46571
CGeotechnical & soil mechanical test47470
DCivil & building7107100
ESteel structure fabrication & erection101210120
FTank fabrication & erection101210120
GMechanical installation121512150
HPiping151915190
ICathodic protection151717192
JElectrical151816191
KTelecommunication192119210
LInstrumentation212721270
MFinal documentationL273427340
NPrecommissioningM343634360
OCommissioningN363836380