Demand and constraints of each construction site.
| Construction site number | Concrete demand () | Allowable maximum transport time (min) | Maximum time interval between two consecutive deliveries (min) | Each construction site starting time |
| 1 | 150 | 90 | 40 | 9:00 | 2 | 108 | 90 | 40 | 9:00 | 3 | 220 | 90 | 40 | 9:25 | 4 | 96 | 90 | 40 | 10:05 | 5 | 172 | 90 | 40 | 10:40 | 6 | 140 | 90 | 40 | 11:10 | 7 | 267 | 90 | 40 | 13:00 | 8 | 162 | 90 | 40 | 13:00 |
|
|