Application of Grey Deformation Prediction Model Optimized by Double Coefficient for Tailings Dam

Table 11

Comparison and verification of stage 9 prediction results (extrapolated value).

Monitoring contentMonitoring pointGM (1, 1)GM-LTGM-WCGDPM-DCDifference ofrelative error/%
Relative error/%Relative error/%Relative error/%Relative error/%

Vertical deformation/mmSZY-01−1.85−3.19−1.1−0.631.42
SZY-02−1.97−3.39−1.43−0.981.28
SZY-03−1.67−3.11−0.84−0.291.58
SZY-04−1.71−3.07−1.04−0.581.36
SZY-05−1.58−2.97−1.27−1.000.94
SZY-06−1.49−2.94−1.18−0.651.22

Transverse deformation/mmCXY-01−3.89−8.59−2.91−0.464.67
CXY-02−1.51−5.72−1.03−0.732.02
CXY-03−2.95−7.53−2.17−0.593.63
CXY-04−1.02−5.00−0.31−0.351.76
CXY-05−2.99−7.90−1.83−0.353.89
CXY-06−0.57−4.860.14−0.071.79

Seepage pressure/kPaSYJ-01−11.14−10.51−10.26−3.457.19
SYJ-02−10.33−10.04−9.56−3.256.73
SYJ-03−11.13−10.50−10.25−3.257.38
SYJ-04−10.01−9.71−9.25−2.966.70
SYJ-05−10.92−10.31−10.04−2.797.63
SYJ-06−10.81−10.54−10.04−3.716.75