A Genetic Algorithm Model for Human Resource Management Optimization in the Internet Marketing Era
Table 1
Symbol definitions.
Problem parameters
Symbolic meaning
Activity z of project y
Uyz
Immediately preceding activity set of activity z of item y.
TU
Total number of projects
Ty
Total number of activities for project y
TR
Total number of employees x
N
Upper limit of multiproject construction period
Nyz
Work quota for activity z of project y
Tyz
Set the number of employees assigned to activity z in project y.
Tx
Set the maximum number of employees that can be allocated in each period.
Zxyz
Man hour factor for employee x to complete activity z of project y.
x ∈
Employee x is in the personnel combination of mode .
B(y, z)
Set of feasible execution modes for activity z of project y. B (y, z) is composed of execution modes that simultaneously satisfy formulas (1), (2) and (8).
K
Number of types of material K
Uk
Unit price of material K
Lyzk
Limit of material k for activity z of project y
Φxk
Employee x’s material k consumption rate
Jyzwn
The activity z of project y adopts mode and starts at time n. The value is 1. Otherwise, the value is 0.
Ixyzn
When employee x is assigned to activity z of project y in time period, the value is 1. Otherwise, the value is 0.
Φyzwk
The sum of the consumption rate of material k under the employee combination of mode for activity z of project y,
dyzw
Construction period of activity z of project y when mode is adopted. The value of dyzw is the smallest integer satisfying formulas (1) and (2) below.