Research Article
Intelligent Generation and Analysis of the Municipal Road Construction Scheme Based on the KNN Algorithm
Table 6
Specific overview of the expressway project.
| Serial number | Basic information | Value |
| 1 | Construction period | 24 months | 2 | Road type | Highway | 3 | Road class | Level 1 | 4 | Project budget | 302 million yuan | 5 | Start and end station number | K32 + 200-K41 + 500 | 6 | Design width range (m) | 12.25–24.5 | 7 | Number of lanes | | 8 | One-way or two-way | Two-way | 9 | Quantity of earthwork excavation (10,000 m3) | 143.5 | 10 | Quantity of earth-filling and stonework (10,000 m3) | 135.4 | 11 | Design life | 100 | 12 | Pavement type | Asphalt road |
|
|