Research Article

Intelligent Generation and Analysis of the Municipal Road Construction Scheme Based on the KNN Algorithm

Table 8

Comparison of characteristic parameters of similar road projects.

Related informationThis projectNo. 26No. 20No. 7

Case name
Similarity0.9190.8140.771
Road classHigh speedHigh speedHigh speedHigh speed
Road length (km)6.126.1269.515.802
Bridge length (km)3.185.0411.22.515
Tunnel length (km)0001.319
Box culvert length (km)00.5280.8561.03
Total excavation volume (10,000 m2)143.5144.2755.7882.229
Total excavation volume (10,000 m)19.54164.876
Total fill volume (10,000 m2)135.4104.38113.10987.579
Total volume of rock fill (10,000 m2)88.84373.204
TopographyMountainMountainMountainHills
Natural divisionV1V1V2V2
Engineering geology0.350.450.550.5
Total valid working days (days)450600500600