Intelligent generation scheme construction method part.

Sub-project, mechanical configuration plan nameProcess, machine name, etc. PijContent

Construction preparations (P1)Preparation of construction technical documents(1) Drawing review. (2) Management requirements. (3) Technical disclosure.
Engineering measurementMeasurement site and requirements.
Construction site layoutSetting requirements for project department, mixing station, steel bar processing plant, construction access road, etc.

Process test (P2)Test monitoring indicators(1) Test items. (2) Measurement data requirements.
Construction of the test section(1) Filling test construction. (2) Earth-rock filling test construction. (3) Measurement method.

Subgrade filling (P3)Substrate treatment(1) Removal of base vegetation and backfilling of potholes. (2) Loosening and rolling of base soil. (3) Base test.
Layered pavingEarthwork: (1) Fully vertical and horizontal layered filling. (2) Construction standards for inclined filling. Earth and stonework: Horizontal filling layer-by-layer.
LevelingThe pusher is used for initial leveling, and the leveling is manually coordinated with the grader. The moisture content is controlled to 2%.
RollingFilling: (1) Rolling parameters are according to the requirements of the test section.
Compaction and fill level inspectionEarthwork: (1) Inspection of packing. (2) Layered compaction. (3) Compaction quality inspection. Earthwork: (1) Compaction quality inspection. (2) Compaction settlement difference detection method.

Subgrade excavation (P4)Construction lofting(1) Check the geological conditions. (2) Stake out the boundary of the excavation.
Layered excavationEarthwork: (1) Excavation from top to bottom, requirements for deep excavation sections. (2) Requirements for zero-filled sections. Stonework: (1) Excavate mechanically as much as possible and use smooth blasting and small charge for the rest controlled blasting. (2) Blasting method process and requirements.
Loading and transportationThat meets the requirements of subgrade filling shall be transported to the fill, and the rest shall be transported to the spoil site.
Clear the bottom and brush the slopeAfter mechanically brushing the slope, the square grid method is manually used to control the flatness.

Special roadbed treatment (P5)Shallow excavation of roadbedReplacement with 1.2 m thick sand and gravel.
Soft baseWhen it is shallow, excavate it directly and replace it with gravel soil or pebble gravel soil.
High fill embankmentLaying the sheds and set up ramps during construction.
Deep diggingGrade 5 frame anchor protection for the slope subgrade.
Fill and cut junctionSet up a transition section not less than 10m.

Hot hammer asphalt pavement (P6)Construction preparationSite cleaning and construction lofting.
Asphalt mixture mixingFactory mixing method and heating temperature requirements.
TransportationShipping time and unloading requirements.
PavingTwo paving machines on the lower layer are paving at the same time. A single machine on the upper layer is paving.
CompactionInitial pressure is light, the recompression is heavy, and the final pressure is light.
Seam treatmentHorizontal seams with flat seams and longitudinal with thermal seams.