Research Article
Prediction of the Normalized COVID-19 Epidemic Prevention Costs of Construction Projects Based on an Optimized Neural Network
Table 7
Sensitivity and ranking of factors that affect the epidemic prevention expenses of the normalized COVID-19 epidemic.
| Factors | First | Second | Third | Fourth | Fifth | Mean value | Sort |
| Project category | 0.14 | 0.16 | 0.15 | 0.15 | 0.15 | 0.15 | 2 | Total investment | 0.25 | 0.25 | 0.26 | 0.24 | 0.24 | 0.25 | 1 | Construction period | 0.09 | 0.10 | 0.08 | 0.10 | 0.10 | 0.10 | 5 | Number of outbreaks during the project construction period | 0.09 | 0.09 | 0.07 | 0.08 | 0.08 | 0.08 | 7 | Number of managers | 0.09 | 0.08 | 0.09 | 0.10 | 0.10 | 0.09 | 6 | Number of construction workers | 0.13 | 0.13 | 0.12 | 0.15 | 0.15 | 0.13 | 4 | Construction scale | 0.18 | 0.15 | 0.12 | 0.12 | 0.12 | 0.14 | 3 | Whether it belongs to a smart site | 0.02 | 0.02 | 0.07 | 0.06 | 0.06 | 0.05 | 8 | Qualification level of the construction subject | 0.02 | 0.02 | 0.06 | 0.00 | 0.00 | 0.02 | 9 |
|
|