Novel Probabilistic Approach for Quantification of Cost-Overruns Risk and Determination of Primary Causes

Table 1

Scheduled material.

Task nameConcrete (m3)Steel (m3)Rebar (m3)

Section A B2383.36404.600368
Section A B1420.70105.048412
Section B B2855.273010.263276
Section B B1822.99709.875964
Section C B21,091.306013.095672
Section C B11,554.421018.653052
Section D B21,032.931012.395172
Section D B11,235.256014.823072
Section A F141.082215.1850.246492
Section A F20204.2030
Section A F32.296174.3290.013776
Section A F416.515165.990.09909
Section A F56.318161.7180.037908
Section A F611.399162.3450.068394
Section A F76.351158.3920.038106
Section A F86.003159.3270.036018
Section A F981.103163.3610.486618
Section B F114.803263.1640.088818
Section B F20299.9530
Section B F313.086263.4090.078516
Section B F486.639191.3550.519834
Section B F54.563183.2540.027378
Section B F671.109189.0510.426654
Section C F150.791214.7250.304746
Section C F20223.3350
Section C F321.313223.9910.127878
Section C F425.23228.9240.15138