Novel Probabilistic Approach for Quantification of Cost-Overruns Risk and Determination of Primary Causes
Table 3
Material parameter settings in case study.
Parameters in material
Material type
Concrete
Steel
Rebar
μ
1.2
1.2
1.2
σ
0.5
0.5
0.5
Price
450
27,846
36,895
The unit of price is yuan (CNY).