Table 1
Progress plan variance and response.
| Construction procedure | | Construction of external wall scaffold | Construction of external wall protective net | Exterior wall coating construction |
| Schedule | | 4th floor | 3th floor | 4th floor | Actual progress | | 4th floor | 4th floor | 3th floor | Schedule variance | | 0 | +1 | −1 | Plan adjustment | | 0 | −1 | +1 | Resource response | Artificial | 0 | Workers—2 | +3 | | Material science | 0 | 0 | Paint +10 barrels | | Mechanics | 0 | 0 | 0 |
|
|