Research Article

Calculation of Buffer Size on Critical Chain Based on Duration Distribution, Multiresource Constraints, and Relay Potential

Table 3

Buffer calculation.

Type of activitiesSerial number of activitiesActivity numberThree-parameter β distributionb-mMedian (T50%)T95%Safety time stiResource impact coefficient RiRelay potential GFree float FFThe initial buffer BThe remaining buffer KFeeding buffer FBProject buffer PB

Critical chain activity1A(1, 2, 3)11.982.630.651.4804.715.97
2B(4, 6, 9)36.147.81.660.590.390
4D(2, 4, 7)34.135.771.641.360.260
5E(5, 8, 12)48.1310.42.271.540.570
9I(2, 4, 7)34.15.751.651.17−0.10

Non-critical chain activity3C(2, 3, 5)23.144.181.040.11−0.213
7G(3, 5, 8)35.116.811.70.480.7212.261.261
6F(2, 4, 6)24.025.221.20.4204.141.701.7
8H(1, 4, 6)23.915.331.420.480.290.191.8101.81