Calculation of Buffer Size on Critical Chain Based on Duration Distribution, Multiresource Constraints, and Relay Potential

Table 4

Comparison of buffer size and project duration of each calculation method.

Name of methodsFactors considered in the methodFBG/dayFBF/dayFBH/dayPB/dayProject planning time/day

Cut and pasteSafety time of activity1.51.51.5731
Root variance methodVariance of activity3326.7830.78
APRT methodResource utilization5.475.475.4712.3636.36
Huchen’s methodProject duration risks and multiple resource constraints1.152.872.656.4431.11
Method used in this paperProject duration risks, multiple resource constraints, and relay potential11.71.815.9730.45