Calculation of Buffer Size on Critical Chain Based on Duration Distribution, Multiresource Constraints, and Relay Potential
Table 4
Comparison of buffer size and project duration of each calculation method.
| Name of methods | Factors considered in the method | FBG/day | FBF/day | FBH/day | PB/day | Project planning time/day |
| Cut and paste | Safety time of activity | 1.5 | 1.5 | 1.5 | 7 | 31 | Root variance method | Variance of activity | 3 | 3 | 2 | 6.78 | 30.78 | APRT method | Resource utilization | 5.47 | 5.47 | 5.47 | 12.36 | 36.36 | Huchen’s method | Project duration risks and multiple resource constraints | 1.15 | 2.87 | 2.65 | 6.44 | 31.11 | Method used in this paper | Project duration risks, multiple resource constraints, and relay potential | 1 | 1.7 | 1.81 | 5.97 | 30.45 |
|
|