Table 4
The cost analysis results of four disposal alternatives (unit: USD/bundle).
| ā | Tunnel excavation | Disposal hole | Bentonite | Canister | Backfilling | Unit cost per bundle | Cast iron | Copper |
| KRS-1 | 20.94 | 138.99 | 79.37 | 135.87 | 177.93 | 73.10 | 626.20 | A-KRS-1 | 14.80 | 83.95 | 55.24 | 51.24 | 199.73 | 51.69 | 456.65 | A-KRS-21 | 8.02 | 75.52 | 45.52 | 79.10 | 235.74 | 28.00 | 471.90 | A-KRS-22 | 8.02 | 75.52 | 42.05 | 79.10 | 235.74 | 28.00 | 468.43 |
|
|