SG dismantling working time.
| | Work | Man-hour |
| | Install of temporary auxiliary crane | 4 | | Installation of temporary lifting device of SG | 80 | | Install of rail and transportation cart | 24 | | Install protection plate | 12 | | Remove SG thermal insulation | 9 | | Transport SG thermal insulation | 8 | | Cut main steam pipe | 8 | | Cut main water supply pipe | 4 | | Cut others pipe | 9 | | Cut cold leg pipe | 9.5 (remote) + 13.5 | | Cut hot leg pipe | 10.5 (remote) + 13.5 |
|
|