Prediction of Bench Blasting Vibration on Slope and Safety Threshold of Blasting Vibration Velocity to Undercrossing Tunnel
Table 3
Monitoring data on the slope surface.
| Blasting times | Horizontal distance (m) | Vertical distance (m) | Maximum charge per delay (kg) | PPV (cm/s) | PVS (cm/s) | x | y | z |
| 1 | 69 | 25 | 250 | 6.9 | 2.5 | 7.2 | 7.9 | 2 | 97 | 51 | 250 | 4.2 | 3 | 4.8 | 5.4 | 3 | 98 | 39 | 315 | 3.4 | 0.9 | 3.6 | 3.8 | 4 | 367 | 65 | 315 | 0.4 | 0.3 | 0.5 | 0.6 | 5 | 193 | 28 | 108 | 1.3 | 1.4 | 1.6 | 2.1 | 6 | 219 | 41 | 108 | 0.6 | 0.9 | 0.4 | 1.0 | 7 | 155 | 54 | 108 | 1.1 | 1.3 | 1.3 | 1.6 | 8 | 133 | 28 | 108 | 1.7 | 1.4 | 1.8 | 1.9 | 9 | 61 | 39 | 310 | 7.6 | 5.8 | 7.7 | 7.9 | 10 | 306 | 65 | 310 | 0.7 | 0.7 | 0.9 | 1.1 |
|
|