The model group with different hole network parameters.
| Model number | Hole depth (m) | Blasting delay between holes (ms) | Blasting delay between rows (ms) | Hole distance (m) | Row spacing (m) |
| 1 | 15 | 60 | 120 | 5 | 4 | 2 | 5 | 5 | 3 | 6 | 5 |
|
|