Safety Early Warning Research for Highway Construction Based on Case-Based Reasoning and Variable Fuzzy Sets

Table 4

Investment cost risk calculations for Contract F 10,000 Yuan.

TimeNumber of project changes this monthInvestment cost deviation value (accumulated Change)Earned valueInvestment cost deviation rateProgress deviation rate

2003.2−1,614.12017,605.669−0.2122−0.1856
2003.3−140−1,754.12018,463.625−0.2073−0.2050
2003.40−1,754.12018,993.87−0.1950−0.2050
2003.5100−1,654.12019,474.723−0.1746−0.1911