Table 4
Investment cost risk calculations for Contract F 10,000 Yuan.
| Time | Number of project changes this month | Investment cost deviation value (accumulated Change) | Earned value | Investment cost deviation rate | Progress deviation rate |
| 2003.2 | | −1,614.1201 | 7,605.669 | −0.2122 | −0.1856 | 2003.3 | −140 | −1,754.1201 | 8,463.625 | −0.2073 | −0.2050 | 2003.4 | 0 | −1,754.1201 | 8,993.87 | −0.1950 | −0.2050 | 2003.5 | 100 | −1,654.1201 | 9,474.723 | −0.1746 | −0.1911 | 2003.6 | 366.6441 | −1,287.476 | 9,317.278 | −0.1382 | −0.1427 | 2003.7 | 200 | −1,087.476 | 9,306.476 | −0.1169 | −0.1179 | 2003.8 | 0 | −1,087.476 | 9,698.879 | −0.1121 | −0.1179 | 2003.9 | −80 | −1,167.476 | 9,942.413 | −0.1174 | −0.1277 |
|
|