Research Article

Diagnosis of Critical Risk Sources in the Operation Safety of the Central Route Project of South-to-North Water Diversion Based on the Improved FMEA Method

Table 4

The ranking of , , , , and the final RPN values of each risk factor.

Risk factorIRPNSort

Storm flood F10.00760.32290.97700.20950.07440.12490.12201
Geological disaster F20.21560.11510.34810.07990.07180.07580.02643
Extreme weather F30.28850.03650.11230.03050.04120.03550.004010
Design safety factor F40.26260.08570.24610.12150.06370.08800.02174
Building reliability F50.31100.06530.17350.08110.05690.06800.01185
Equipment reliability F60.31380.01570.04770.06640.03910.05090.002414
Geological conditions F70.29140.10550.26570.22020.07340.12710.03382
Engineering construction quality F80.24290.09340.27770.01650.06080.03160.00886
Personnel management quality F90.31080.03320.09660.04550.04060.04300.00429
Engineering maintenance management level F100.30560.03170.09400.02280.04090.03050.002912
Management system perfection level F110.31390.01560.04730.02280.03820.02950.001418
Human activity impact F120.30240.05230.14740.02030.04720.03090.00468
Operation and maintenance construction management level F130.32040.01700.05030.00400.03910.01250.000619
Protection scope violation activity F140.30750.04690.13230.01160.04570.02300.003011
Illegal operation F150.32200.00340.01040.00590.03660.01470.000220
Man-made sabotage F160.29930.04530.13160.00260.04570.01090.001417
Fire F170.29850.03850.11430.01270.04370.02360.002713
Sudden water pollution F180.30300.05480.15310.01990.05000.03150.00487
Traffic accident F190.29900.03810.11310.00430.04380.01380.001616
Social dispute F200.28170.05630.16670.00200.04730.00960.001615