Simulation Calculation of the Collapse Process of High-Rise Steel Structure Energy-Forming Cutting Blasting Demolition
Table 2
Construction network schedule.
Serial number
Process name
Days 1-3
Days 4-6
Days 7-10
Days 11-14
Days 15-19
Day 20
1
Mobilization preparation: mobilization of personnel and equipment, erection of temporary facilities, erection of water and electricity pipelines, and handling of administrative permit for blasting operation
3 days
2
Erection of predemolition platform
3 days
3
Predemolition
4 days
4
Shaped energy cutter, parameter determination, customization
4 days
5
Arrange warning points, conduct the first explosion test, and cut off the directional window
5 days
6
Install the shaped energy cutter according to the construction scheme